America’s missile stockpiles will take years to rebuild—a watchdog warns of Pentagon’s blind spot

Over the past decade, the U.S. military bought an average of 86 Tomahawk cruise missiles a year. In the war with Iran, it has fired more than 1,000, according to the Center for Strategic and International Studies (CSIS).
That math explains why stockpiles of two of America’s most relied-upon weapons, the Tomahawk and the Patriot air-defense interceptor, will take years to refill. Under current Pentagon delivery projections, CSIS estimates the Tomahawks fired at Iran won’t be fully replaced until late 2030. The Army’s 3,203 Patriot interceptors requested for fiscal 2027 aren’t projected to start arriving until May 2029.
A new watchdog report says the Pentagon isn’t organized to close that gap. In “DOD Munitions: Planning and Leadership Needed to Address Persistent Shortages,” released Nov. 19, the Government Accountability Office (GAO) found that the Defense Department has no overarching plan linking munitions production and funding to its requirements, and no office with the authority to carry one out. Fortune reported on the GAO’s findings this week.
Why Tomahawks and Patriots are so hard to replace
Both weapons are Cold War designs. The National Air and Space Museum says Tomahawks were developed in the late 1970s and became fully operational in the early 1980s. The Patriot’s precursors date to the mid-1960s, and systems comparable to today’s arrived in the early 1980s, per CSIS.
The Tomahawk is a ship- and submarine-launched cruise missile with a range of roughly 1,000 miles. The Patriot is a defensive system that can intercept incoming missiles, drones, and manned aircraft, per Raytheon. Besides the U.S., four allies field Tomahawks: the U.K., Australia, the Netherlands, and Japan. Raytheon, a unit of RTX, makes every Tomahawk in the U.S., and RTX is No. 49 on the 2026 Fortune 500. The U.S. and 18 other countries operate the Patriot, and several other nations, including Germany and Japan, also manufacture Patriot systems.
The Iran war, which the U.S. and Israel launched on Feb. 28, drew both stockpiles down fast. U.S. destroyers and submarines have fired about a third of the prewar Tomahawk inventory, and about two-thirds of the prewar Patriot interceptor inventory has been expended against Iranian ballistic missiles, according to an updated CSIS analysis. Transfers to Ukraine had already thinned Patriot stocks.
Production hasn’t kept pace because orders didn’t. Recent Tomahawk output has run below 200 missiles a year, though Raytheon aims for capacity of more than 1,000, CSIS found. Lockheed Martin, which builds the Patriot’s PAC-3 MSE interceptor, makes about 600 a year and is targeting 2,000 a year by 2030.
New interceptors will be spoken for quickly. CSIS estimates about 1,600 were already in the allied backlog before the war, and coalition partners that fired their own Patriots during the Iran war have since bought more.
What the GAO found, and what it couldn’t say
The GAO’s public report doesn’t say which munitions are short. It is a version of a classified report issued Sept. 24, and the Pentagon deemed inventory trends and persistent shortfalls too sensitive to release. The public version lays out a management problem.
“DOD does not have an overarching plan that links munitions production and funding to requirements,” the auditors wrote. “According to DOD officials, in lieu of a plan, DOD and the services can be reactive to global events rather than driven by total requirements.”
The report cites the Army’s push to produce more 155-millimeter artillery shells, which addressed shortages worsened by U.S. support to allies but “was not driven by DOD’s total munitions requirement.” Without a plan that sets long-term goals and metrics, the GAO warned, the Pentagon risks persistently low inventories, or “investing in munitions that are projected to exceed the total munition requirement.”
Leadership is spread thin. Each service manages its own stockpile; for example, the Navy’s Tomahawk Weapon System Program Office oversees the Navy’s inventory. A Munitions Acceleration Council created in July 2025 to speed missile production still had no formal signed charter as of November 2026, a senior Pentagon official told the GAO.
Service officials told auditors that without a dedicated leadership office, “it may be difficult to realize progress in addressing munitions shortages at any level.” The GAO made four recommendations, including that the Pentagon write an overarching munitions plan and name an office with the authority to carry it out. The department generally concurred.
The stakes are financial and military. A plan could guide how the Pentagon spends at least $25 billion Congress appropriated in 2025 for munitions, the GAO noted.
Experts split on whether planning or capacity is the real bottleneck
“The GAO findings illustrate what everyone can see with their own eyes,” Michael Horowitz, senior fellow for technology and innovation and director of the Defense and National Security Program at the Council on Foreign Relations, tells Fortune.
His prescription is to change what the Pentagon buys. “The single most important thing the Pentagon needs to do is continue ramping investments in precise mass systems like inexpensive cruise missiles and long-range, one-way attack drones,” Horowitz says, “because the supply chains and production processes will be easier. This will build resiliency and redundancy into the system.”
Michael O’Hanlon, director of foreign policy research and a senior fellow at the Brookings Institution, puts less weight on the missing plan. “I don’t see it quite this way,” he tells Fortune. “DoD is scurrying constantly to work with industry to scale up production of key munitions. The issue is less the absence of a single formal plan on paper and much more physical constraints limiting capacity. A better plan might help, but it’s not the core issue or driver.”
CSIS reached a similar conclusion in May: With bipartisan support in Congress for munitions funding, the constraint is no longer money but the time it takes to expand capacity and build complex weapons.
Elaine McCusker, a senior fellow at the American Enterprise Institute and former acting undersecretary of defense (comptroller), sees both forces at work. Asked about the main obstacles to replenishment, among them factory capacity, supply chains and critical materials, contracting, and unpredictable demand, she added one more.
“I would add workforce to that, which is also negatively impacted by the ups and downs of the budget and requirements demand,” McCusker says. “I think two things drive the time it takes to rebuild the stockpile: predictable resourcing to make the most of, and expand, the production capacity of current manufacturing and supply chains and the urgency placed on developing, testing and producing entirely new munitions — and interceptor — solutions.”
Her fix starts with the budget. “Fully fund the military budget on time each fiscal year,” she says. “Fund full automation of the Pentagon inventory, parts, and supply system, which is a key component of solving material weaknesses for the department to pass a full financial statement audit, but more importantly, as we see with munitions, it is necessary for readiness and munitions stockpile planning.”
What to watch
The next test is the fiscal 2027 budget. The administration has requested $1.5 trillion for defense, including 785 Tomahawks and 3,203 Patriot interceptors, though CSIS doubts Congress will pass the full request. Also watch whether the Pentagon names an office to own the munitions problem, as the GAO recommended.
Even if Congress funds every missile on time, the timeline is long. The first Tomahawks from the 2027 order aren’t projected to reach U.S. inventories until March 2030, after nearly three years of production lead time.